Re: Enterprise Resource / multiple projects ?
From: Dale Howard [MVP] ("Dale)
Date: 04/08/04
- Next message: Dale Howard [MVP]: "Re: Creating an OLAP cube using Global Template fields"
- Previous message: Dale Howard [MVP]: "Re: portfolio analyzer"
- In reply to: JeffP: "Enterprise Resource / multiple projects ?"
- Messages sorted by: [ date ] [ thread ]
Date: Wed, 7 Apr 2004 18:49:51 -0600
JeffP --
There are two ways that the owner of Project B could learn of the resource's
misfortune:
1. The owner of Project A calls the owner of Project B, knowing that
Project B is dependent on project A..
2. The owners of Projects A and B have set a cross-project dependency
between the dependent tasks in each plan. After the resource's accident,
the owner of project A reschedules the task 1 week later and saves the
project. The next time the owner of project B opens the plan, he/she will
see that the external predecessor task has slipped one week, driving the
task in project B one week late as well.
The first option would be my personal preference, as I believe the use of a
software tool can never replace good project communication. Hope this
helps.
-- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "JeffP" <anonymous@discussions.microsoft.com> wrote in message news:96B8434A-8B9B-4827-8DAE-FA675FF0E9AE@microsoft.com... > Hi, > > I have the following question for project server experts: > > Project A has activity 1 using Ent resource 1 (activity is sched to end 5/2/04) > Project B has activity 1 using Ent resource 1 (activity is sched to start 5/3/04) > so far no problems, all planning is done and project files saved to the server. > Ent resource 1 is hit by a car and this delays the finish of proj A-activity1 by 1 week. > > my question: > the owner of project b may not even work in the same country as the owner of project a, > how do they find out that proj B-activity 1 is going to be delayed a week or do they have to relevel their project to see the change in start date? > > tia > Jeff > > ps i have tried to model this problem but with inconsistent results.
- Next message: Dale Howard [MVP]: "Re: Creating an OLAP cube using Global Template fields"
- Previous message: Dale Howard [MVP]: "Re: portfolio analyzer"
- In reply to: JeffP: "Enterprise Resource / multiple projects ?"
- Messages sorted by: [ date ] [ thread ]
Relevant Pages
|