Re: who does when what report
From: Arun (anonymous_at_discussions.microsoft.com)
Date: 03/05/04
- Next message: Stephanie: "Fiscal Year in Portfolio Analyzer"
- Previous message: Lee: "Re: RBS Structure and Time*** Approval"
- In reply to: John Beamish: "Re: who does when what report"
- Next in thread: Dale Howard [MVP]: "Re: who does when what report"
- Reply: Dale Howard [MVP]: "Re: who does when what report"
- Messages sorted by: [ date ] [ thread ]
Date: Fri, 5 Mar 2004 04:41:09 -0800
Hi,
I am able to short list the task but in this method a couple of task which have actuals booked in the specified period gets missed out.
The scenario is this. I have 10 tasks named from task1 to task10. i want to list the task name along with the actual hours booked for a period irrespective of their start and end dates. if for the period 16-feb to 20feb i have only the actuals entered against task1, task6, task8 then i need to display only these 3 tasks..
is there anything i need to include in the filter criteria.?
thanks.
----- John Beamish wrote: -----
The Who Does What When report uses the filter "Resources - Work"
First, build the appropriate filter:
1. Project | Filtered for | More filters ...
2. Click on the Resource radio button
3. Click on "Resources - Work"
4. Click on Copy
There is already one filter condition being applied. We have to add
several additional ones.
5. add a row
And/Or = And
Field Name = Actual Work
Test = is greater than
Values = 0h
6. Add a row
And/Or = And
Field Name = Start
Test = is greater than
Values = "Enter earliest start (mm/dd/yyyy)"? NOTE: you _must_ include
the quotes and the question mark.
7. Add a row
And/Or = And
Field Name = Start
Test = is less than
Values = "Enter latest start (mm/dd/yyyy)"? NOTE: you _must_ include the
quotes and the question mark.
This filter will pick up tasks with the start date in the specified
range. The test for Actual Work may not be necessary, but I've included
it anyway.
Click on OK and Close to exit from preparing the filter.
8. View | Resource Usage and make certain the right hand side of the
display is showing Actual Work. In the Formatting tool bar, select the
filter you just created to demonstrate that it works and to show the items
that will be selected.
9. Click on View | Reports | Assignments | Who Does What When and click
on the Edit button.
10. On the definition tab, change the filter to the one you just created.
11. On the sort tab, change the sequence to Name ascending.
JLB, PMP
On Thu, 4 Mar 2004 01:16:08 -0800, Arun
<anonymous@discussions.microsoft.com> wrote:
> Hi,
>> is there any way that i can show only the tasks which have actuall
> booked for the date range that i specify.
> Now when i take the above said report...i can see the list of tasks
> assigned to the resource & the actual work put against each task on day
> basis is shown.
>> Since the task list is so huge i see all the task irrespective of
> actuals booked or not. I want to restrict this report to display only
> the task which have actuals booked.
>> can anyone suggest me in this regards??
>> cheers
--
- Next message: Stephanie: "Fiscal Year in Portfolio Analyzer"
- Previous message: Lee: "Re: RBS Structure and Time*** Approval"
- In reply to: John Beamish: "Re: who does when what report"
- Next in thread: Dale Howard [MVP]: "Re: who does when what report"
- Reply: Dale Howard [MVP]: "Re: who does when what report"
- Messages sorted by: [ date ] [ thread ]