can't rename projects
From: Michael (anonymous_at_discussions.microsoft.com)
Date: 02/03/04
- Next message: Kasper Ovi: "Re: OLAP Cube - solution found!"
- Previous message: Michael: "Re: Modified Project Name in PWA"
- Next in thread: Dale Howard [MVP]: "Re: can't rename projects"
- Reply: Dale Howard [MVP]: "Re: can't rename projects"
- Messages sorted by: [ date ] [ thread ]
Date: Tue, 3 Feb 2004 00:28:25 -0800
also entered this as a reply to an old post, but to
increase chances of a quick reply, listed it as a new post
as well...
Michael
----------------
Hi Dale,
I have the following problem:
1) I start with a blank project plan with a file
name "template.mpp". The plan has some default task
names, column names, embedded macros, etc., specific to
our organization
2) I intended to have users make a copy of the template
and rename it, then upload it to the server
3) however, when they upload it, then view their new
project from project view, the task on line 0 of the
project still says "template". It should have the
modified name of the plan.
I believe this is related to the problem you discussed
here below. However, when I got to step 8, the option you
mentioned was grayed out. I tried to solve this by
creating an enterprise account, but when I closed out and
logged on with the newly created enterprise account, I got
a message saying that I was unable to connect. Of the
possible problems listed, the most likely cause was a lack
of an enterprise global template.
Furthermore, when I try "Tools >>> enterprise Options >>>
Restore Enterprise Global" I get a message saying that the
action cannot be reversed. Thus I am wary of restoring
the template until I fully understand the implications
(since several projects are already using the server).
Can you give some advice?
And if there is a simpler workaround/solution available
for renaming a project (that doesn't require enterprise
features), please let me know. It seems like the more
features I am required to use to accomplish a desired
task, the more likely I am of screwing something up, so
simpler is better :-)
>-----Original Message-----
>Scott --
>
>Use the following steps to rename your project:
>
>1. Log into Project Web Access
>2. Go to the Updates page
>3. Make certain that you don't have any unprocessed task
updates in the
>project (if you do, update them into the plan)
>4. Open the project in question in Microsoft Project
>5. Click File - Save As then click the Save as File
button
>6. Save the file as an .mpp file
>7. Ask your Project Server administrator to delete the
project from the
>Project Server database
>8. Import the project into the database using Tools -
Enterprise Options -
>Import Project to Enterprise
>9. Save and publish the project
>
>Hope this helps.
>
>--
>Dale A. Howard [MVP]
>Enterprise Project Trainer/Consultant
>http://www.msprojectexperts.com
>"We wrote the book on Project Server"
>
>
>"Scott" <anonymous@discussions.microsoft.com> wrote in
message
>news:744901c3e768$29a57470$a001280a@phx.gbl...
>> Hi, there,
>> We are using MSP 2002 and PWA. Can I modified the
project
>> name in PWA? Or I have to delete this project and upload
>> the project with a new name again? Thanks. Scott
>
>
>.
>
- Next message: Kasper Ovi: "Re: OLAP Cube - solution found!"
- Previous message: Michael: "Re: Modified Project Name in PWA"
- Next in thread: Dale Howard [MVP]: "Re: can't rename projects"
- Reply: Dale Howard [MVP]: "Re: can't rename projects"
- Messages sorted by: [ date ] [ thread ]