Re: How mark a project as completed?
- From: Allen Watson <allen@xxxxxxxxxxxxx>
- Date: Sat, 20 Aug 2005 11:58:18 -0700
On 2005-08-19 18:01:07 -0700, James Stover <stoverje@xxxxxxxxxx> said:
In the Project Center, how do I mark a project as completed so it doesn't keep saying it is past due? I still want to see the project and it's data for reference.
Thanks,
Jim
On the Overview panel of the project, click the Properties button at the bottom, and uncheck the "Due Date" box.
--
Allen Watson
MVP for Office (Entourage, Word)
http://homepage.mac.com/allen_a_watson/
HELP for Entourage: http://entourage.mvps.org
.
- Follow-Ups:
- Re: How mark a project as completed?
- From: James Stover
- Re: How mark a project as completed?
- References:
- How mark a project as completed?
- From: James Stover
- How mark a project as completed?
- Prev by Date: Re: Entourage Launches Itself
- Next by Date: Re: Sent Items question
- Previous by thread: How mark a project as completed?
- Next by thread: Re: How mark a project as completed?
- Index(es):