Re: Microsoft Visual C#

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



Thanks for the info Steve,

Well, I have already started creating my project and have succesfully setup the menus, forms and datasets that I need to start off with but, when I started researching about importation of data from excel etc, I found very little info. That got me a bit concerned because the package is no good to me without the import from excel function.

Now, that I know this is possible, I can take it further.

regards,

Donovin

"steve.falzon@ noonbay.co.uk" <nospamplease> wrote in message news:9oq993d8u1dp2pltcvvo31mqmcgs8jnnql@xxxxxxxxxx
On Wed, 11 Jul 2007 16:17:47 +0200, "Donovin" <donovin@xxxxxxxxxx>
wrote:

Hi all,

I am looking at writing new software to replace an existing old DOS based
package our company uses for project cost estimating. I have downloaded and
started to learn the in's and out's of microsoft's visual c# but, as I get
more into it, I'm not sure whether it will be able to do all that I'm
looking for.

Basically what I need is:

1. To import a schedule of items from an Excel spreadsheet,
2. Using a database of resources, assign these to individual items in the
schedule and get a cost rate for that item,
3. Print reports that show the schedule items with associated resource costs
etc.

and a number of other functions.

I know this is a very broad question but, before I go and spend too much on
books etc, just wanted to see what kind of feedback I could get and whether
other packages would be more appropriate.

Regards

Donovin


Hi Donovin

I wouldn't worry about the capabilities of c#, the requirments you
give are achievable in c# or other .Net languages.

What is it that has made you doubt whether you can do these things?

By the way, I'd browse the web or usenet for examples of what you are
looking for rather than splash out on books. There are thousands of
fantastic resources on the net.

cheers
Steve

.



Relevant Pages

  • Re: Managing projects with subcontractors
    ... prepare a broad schedule with milestones and include it with the tender. ... This way he would be able to commit for the resources to be made ... As far as cost is concerned, ... You could go one step further and assign Bob The Tiler to each ...
    (microsoft.public.project)
  • Re: Using Project for a Time & Materials contract
    ... > cost associated, in order to have a visual plan to look at. ... > have to have multiple resources for them). ... >> as their availability, etc, impacts the work schedule. ... >> Assigning at that level gives a workload distributed evenly over the task ...
    (microsoft.public.project)
  • RE: Standard Project Template
    ... Thankfully my managers are not worried ... about cost or resources. ... currently underway and remove from the schedule all tasks already completed, ... These can be estimated for duration, and cost ...
    (microsoft.public.project)
  • Re: How to let project assign work to multiple resources unevenly?
    ... If I have to do a task that requires 8 hours and the resource doing it costs $10 per hour, that task will cost $80 whether I schedule it for Monday or Tuesday. ... A project will require X man-hours of work and the pattern in which you assign the resources won't change it. ... Giving someone MS Word isn't sufficient to make them a professional writer, giving them Excel won't make them a mathematician, and giving them Project won't make them a project manager, providing all the management strategic planning and tactical decision making skills that function requires. ...
    (microsoft.public.project)
  • Re: Microsoft Visual C#
    ... package our company uses for project cost estimating. ... To import a schedule of items from an Excel spreadsheet, ... Using a database of resources, assign these to individual items in the ...
    (microsoft.public.dotnet.languages.csharp)