Re: Date minus working days
- From: "Douglas J Steele" <NOSPAM_djsteele@xxxxxxxxxxxxxxxxx>
- Date: Tue, 18 Apr 2006 12:08:17 -0400
Take a look in the Date/Time section of "The Access Web"
http://www.mvps.org/access/
There are a couple of solutions there.
--
Doug Steele, Microsoft Access MVP
http://I.Am/DougSteele
(no e-mails, please!)
"Kerry Purdy" <KerryPurdy@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:25F1C795-C13D-4EAA-A2FB-343839F4E68A@xxxxxxxxxxxxxxxx
Hiya
I have a finish date field, I need to calculate what the date will be 2
working days before, this will give me a start date.
Many thanks
.